Sorting bill-of-quantities lines into a standard
A Machine Learning Approach to Classifying Construction Cost Documents into the International Construction Measurement Standard
Takeoff & estimatingDocument intelligence

What it proposes
Six kinds of model classify 51,906 real bill-of-quantities descriptions from 24 UK infrastructure projects into 32 ICMS categories.
Why it is here
It is the text half of the quantity problem, and the one real-project dataset in this group. It shows that the descriptive language of a bill of quantities is regular enough that simple models sort it, which is the opposite lesson from the drawing papers.
What was evaluated
124,000 priced items from 24 projects of one UK infrastructure contractor, reduced to 51,906 in the 32 categories with enough samples. An 80/20 split, 10,242 test items. A feed-forward network reaches F1 at or above 90% on 25 of the 32 categories; recurrent and convolutional models land close behind, so simpler models compare favourably. Code and the trained model are public; the data is not.
Limits of the evidence
One contractor's wording, UK infrastructure only, and from 2022, before large language models; the cost figures themselves are not predicted.
Evidence check
- Real task?
- Yes. Real bill-of-quantities lines from 24 UK infrastructure projects, labelled by the contractor.
- Repeated runs?
- Not reported.
- Variations tested?
- Two text representations and six model families, from bag-of-words to recurrent networks.
- Failures analysed?
- Partly. Class imbalance is shown; per-category F1 is reported, not an error analysis.
- Data public?
- Code and the trained model on GitHub; the contractor's data is not public.
Worth the full paper?
Worth reading if you map cost lines to any standard, ICMS or your own. The text is the easy part: a 2022 model with no language model behind it sorts it at 90%. The caveat is one contractor's house style, so the first test is a few hundred of your own lines.